Contractor Management Procedures

Procedures for bringing third-party contractors (HVAC, electrical, plumbing, IT, pest control, paint/coating, roofing, landscaping, service technicians, construction) onto Scott Recycling's facility to perform work.

Audience: Facility manager, Dan, office staff, anyone scheduling or supervising contracted work

Why this exists: Contractors introduce three categories of risk that require active management:

  1. Safety risk — untrained outsiders in an industrial warehouse with forklifts, hazmat, and heavy equipment
  2. Liability risk — if a contractor is injured on our property and they're uninsured, Scott Recycling inherits the claim
  3. Business risk — contractors have access to inventory, records, equipment, and our reputation if they do poor work

A documented contractor management process converts ad-hoc relationships into managed ones.

Related: Visitor On-Site Procedures, Workplace Safety, Emergency Response, sr_maintenance module (tracks contractor work orders)


Scope of This Document

Covered: - One-time service calls (repair someone calls) - Scheduled recurring maintenance (HVAC tune-up, pest control, etc.) - Construction projects (building improvements, new equipment installation) - Specialty trades (welding, roofing, paint, concrete)

Not covered: - Employees of Scott Recycling (different HR process) - Customers dropping off material (see Visitor Procedures) - Vendors delivering supplies (also Visitor Procedures) - Temporary labor / staffing agency workers — these are managed under HR as contract employees


Contractor Approval Process

Step 1 — Scope definition

Before reaching out to any contractor, the person requesting the work (Dan, facility manager, department lead) documents:

  • What work needs to be done — as specific as possible
  • Why — urgent repair, preventive maintenance, improvement, compliance-driven
  • Budget — ballpark or authorized maximum
  • Timeline — when it needs to happen, any constraints
  • Access requirements — which zones, hours needed, any special accommodations
  • Impact on operations — does anything need to shut down? Temporary relocations?

This goes into a work request (paper, Odoo helpdesk ticket, or sr_maintenance work order).

Step 2 — Sourcing contractors

For non-urgent work, get at least 2-3 quotes before committing. For urgent or emergency work, use pre-approved vendors first.

Approved contractor list — a running roster of contractors Scott Recycling has used successfully before. Track:

  • Company name
  • Primary contact + phone
  • Services provided
  • Typical rate (or note "project-based")
  • COI on file date
  • W-9 on file date
  • Last used (date + project)
  • Rating / notes (1-5 stars + free text)

Maintain this list in ~/Desktop/sr-drafts/vendor-contacts.md (draft) or after filling in, in sr-docs knowledge-base/vendor-contacts.md.

Step 3 — Insurance verification (BEFORE work begins)

Every contractor must provide:

  • Certificate of Insurance (COI) showing active coverage for:
  • General liability: minimum $1M per occurrence / $2M aggregate (adjust to match your actual requirements)
  • Workers' compensation: if they have employees (required in TN for 5+ employees)
  • Commercial auto: if they drive vehicles on-site
  • Umbrella / excess: for higher-risk work (roofing, welding, etc.)

  • Scott Recycling listed as additional insured on the COI (this is a specific request the contractor's agent handles — not automatic)

  • W-9 for tax reporting (if payments exceed $600/year)

  • Business license in the state they're operating (varies by state/trade)

  • Bond (if required for the specific trade — often required for electricians, plumbers, some general contractors)

Store the COI and W-9 in the contractor's file. Re-verify the COI annually at minimum — insurance lapses without notice and you find out during a claim.

Step 4 — Background check (situational)

For contractors with access to sensitive areas (data destruction, cage area, server closet): - Criminal background check — consider requiring this for workers who will be alone in restricted areas - References — call 2 previous commercial clients to verify quality and behavior

For one-time visits to non-sensitive areas (HVAC in the office, pest control in the break room), background checks are usually skipped but can be required at Dan's discretion.

Step 5 — Written agreement / PO

For any work over $[[threshold — e.g., $500]]:

  • Written quote/estimate from the contractor with clear scope
  • Purchase order from Scott Recycling authorizing the work
  • Signed agreement if the work is ongoing (service contract)
  • Payment terms clarified in writing — Net 30 is standard, avoid COD for contractors

For small emergency repairs, verbal authorization from Dan or the facility manager is acceptable IF documented in the daily log.


On-Site Arrival Procedure

Step 1 — Advance notice

Contractors should have an appointment before arriving. The person who scheduled the work is responsible for:

  • Notifying reception of the expected contractor, company, and arrival window
  • Notifying the zone supervisor whose area will be affected
  • Notifying Dan for anything that affects multiple zones or requires utility shutoffs

Step 2 — Sign-in at reception

All contractors sign in using the visitor log. Additional information for contractors:

  • Company name + vehicle description / license plate
  • Scope of work for this visit (if different from the original agreement)
  • Expected duration
  • Specific areas they'll be working in
  • Host employee responsible for escort and oversight

Step 3 — Contractor safety orientation

Before the contractor begins work, they receive a site-specific safety briefing:

  1. Facility overview — this is a recycling operation, not a standard office or retail space. Active forklifts, chemicals, hazmat, dust, noise.
  2. Hazards they might encounter in their work zone — lead dust (CRT area), battery acid, sharp metal, moving machinery
  3. Required PPE — safety glasses, hi-vis vest, hearing protection where needed, respirator if in CRT or chemical area, hard hat for construction/roofing
  4. Lockout/tagout rules — if they're working on equipment, they must follow our LOTO procedure (not just their own)
  5. Emergency procedures — where to exit, where to assemble, how to call for help
  6. Smoking / fire policy — designated smoking area only, no open flames without a hot work permit
  7. Photography restriction — no photos without Dan's permission
  8. Access restrictions — which zones they are and are NOT allowed in
  9. End-of-day sign-out — must sign out, return badges, ensure tools are secured

Sign-off: contractor signs a brief acknowledgment that they received the safety briefing and agree to follow the rules. This protects Scott Recycling in a claim dispute.

Step 4 — Escort / supervision

Depending on risk level:

  • Low-risk work (office HVAC, pest control in break room): occasional check-ins, no constant escort
  • Medium-risk work (electrical in warehouse, equipment repair): regular check-ins every 30-60 minutes
  • High-risk work (roofing, welding, crane/hoist, hazmat adjacent): constant supervision by a Scott Recycling employee
  • Working alone after hours or in secure zones: not allowed — always supervised

Step 5 — Work authorization per task

If the contractor encounters something unexpected (need to cut into a wall, shut off a utility, access a different area), they should stop and ask for authorization from the host employee or Dan. No scope creep without approval.

Step 6 — Hot work permits

For work involving welding, torch cutting, grinding, soldering, or any open flame:

  • Required: signed hot work permit from Dan or facility manager
  • Fire watch required during and 30 minutes after hot work
  • Fire extinguisher within arm's reach
  • Area cleared of flammable material
  • Sprinkler system operational
  • Time-limited — permit is for a specific day and work area

During the Work

Check-in cadence

The escort / host employee checks on the contractor periodically:

  • Are they following the safety briefing?
  • Are they in the zones they should be in?
  • Any unexpected findings or scope changes?
  • Any concerns from the contractor about safety or access?
  • Are they making progress on the agreed scope?

Incident handling

If something goes wrong while the contractor is on-site:

  • Contractor injury: treat as emergency per Emergency Response. Call 911 if serious. Notify Dan immediately. Do not admit fault. Document everything. Notify insurance.
  • Damage to Scott Recycling property: document (photos, scope), ask the contractor to file a claim with their insurance. Do not accept verbal promises — get it in writing.
  • Damage to contractor's equipment: same approach but their claim is typically against their own insurance.
  • Safety violation: stop work immediately, have a conversation, re-brief, document. Repeated violations = terminate the engagement.
  • Theft or suspicious activity: stop work, escort out, document, notify Dan and police.
  • Scope creep requested by contractor: defer to Dan. No unauthorized additional work.

Daily end-of-shift

Before a contractor leaves for the day:

  • Walk the work area with the contractor — visual inspection for unsafe conditions, unfinished work that could injure someone, unsecured tools
  • Confirm work done today vs. remaining scope
  • Lock up any tools the contractor leaves behind
  • Contractor signs out at reception
  • Next-day plan if work continues — what time they'll arrive, any prep needed

Completion & Acceptance

Walkthrough at completion

When the contractor says they're done:

  1. Walk the work area together
  2. Verify the work matches the agreed scope — use the original quote/PO as the checklist
  3. Test functionality — run the equipment, turn on the circuit, flush the line
  4. Document any punch list items — things that still need attention
  5. Photograph the completed work for the file
  6. Sign off on completion (or note punch list remaining)

Final invoice and payment

  • Invoice should match the quote — if it doesn't, question the variance before paying
  • Pay per agreed terms (Net 30 typical)
  • Retain payment records per Record Retention Policy
  • Update the contractor rating in the approved contractor list

Warranty / follow-up

If the work came with a warranty (common for HVAC installs, roofing, equipment repairs): - Document the warranty terms in the contractor's file - Flag warranty expiration in your calendar - File service records for anything that might need warranty service


Contractor Classifications & Insurance Minimums

Trade Typical liability minimum Workers comp Auto Additional
HVAC service $1M/$2M Required if employees Required Freon handling cert
Electrical $1M/$2M Required if employees Required State license
Plumbing $1M/$2M Required if employees Required State license
IT / network $1M/$2M If employees Not required Data security plan for sensitive work
Roofing $2M/$4M Required Required Fall protection documentation
Welding / metal fab $2M/$4M Required Required Hot work cert
Pest control $1M/$2M If employees Required Chemical license
Landscaping $500K/$1M If employees Required
General construction $2M/$4M Required Required State license, bond
Paint / coating $1M/$2M Required Required VOC disposal
Forklift / equipment service $1M/$2M Required Required OEM cert
Cleaning / janitorial $500K/$1M If employees Not required

Adjust minimums up for any contractor working in or near hazmat storage, high-value inventory, or data destruction areas.


Red Flags (Decline or Pause)

If any of these come up, STOP and discuss with Dan before proceeding:

  • Contractor cannot or will not provide a COI
  • COI has expired
  • Worker's comp policy is questionable (e.g., "I'm a sole proprietor so I don't need it" — but then they bring employees)
  • License has been suspended or expired
  • Contractor refuses safety briefing
  • Contractor refuses to sign in
  • Contractor refuses to be escorted
  • Contractor arrives impaired (alcohol, drugs)
  • Contractor wants to work alone in secure zones
  • Contractor's quote is dramatically lower than competitors (suggests corner-cutting)
  • Contractor has multiple complaints on BBB / Google / industry sites
  • Contractor fails to complete prior jobs without explanation
  • Contractor subcontracts the work without telling you (you may end up with an uninsured subcontractor on-site)

Contractor File — What to Keep

For each contractor, maintain a file (physical or digital) with:

  • Intake documents: quote/estimate, PO, signed agreement
  • Insurance: COI, annually renewed
  • Credentials: W-9, license, certifications, bonds
  • Background check: if applicable
  • Safety: signed safety briefing acknowledgment per visit, any incident reports
  • Work records: daily logs, photos, completion walkthroughs, punch lists
  • Financial: invoices, payments, disputes
  • Ratings / notes: quality, reliability, behavior
  • Warranty documents

Retention: 7 years after the contractor's last engagement per Record Retention Policy.


Review Schedule

  • Annually: review approved contractor list, remove inactive contractors, re-verify COIs
  • Per engagement: review this procedure if any incident occurred
  • Triggered: if insurance requirements change (your coverage, state law), update minimums